Downtown ADA, lighting and tree improvements completed

Summary

The city formally closed out Phase II of the downtown improvement project, which came in under the original bid amount, with a final payment of $8,493.71 to the contractor.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jul 7, 2026.

Impact analysis

💰Financial impact

Final construction costs came in about $42,000 under the original bid, with a total project cost of $729,663.26.

✅Who benefits

Downtown residents, businesses and visitors get improved accessibility, lighting and streetscape trees.