$3.085 Million Street Reconstruction Bonds
Summary
The city sold bonds at a favorable 3.7% rate to pay for the 2026 mill and overlay plus Spring Street and Freemouw street projects — the low bid let the city borrow less than planned.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 21, 2026.
Impact analysis
The city will repay $3.085 million in bonds at about 3.7% interest, down from the $3.35 million originally authorized.
Motorists and residents on streets receiving the mill and overlay and reconstruction work.