MediumRoads

Pedestrian crossing at 12th Avenue South and railroad

A resident said she has no safe way to cross 12th Avenue to reach the walking path, with no crosswalk near the railroad tracks and blocked sight lines. Staff will ask the traffic engineer whether a crossing or ramp is feasible, though the railroad and stoplight make it tricky.

1 mention (1 this month)Last discussed Oct 5, 2026
HighRoads

2027 Street, Sewer, Water and Concrete Projects

A batch of 2026 street projects advanced: 17th St/4th Ave N, the 20th–23rd Ave S and 6th–7th St S area, Moorhead Center Mall Phase 3, and planning for 34th St N. Residents in those areas should expect construction and possible special assessments.

3 mentionsLast discussed Sep 28, 2026
HighRoads

Five-Year Capital Improvement Plan 2026-2030

The council teed up next year's petitioned sewer, water, and concrete repair work, a 50th Ave S street light project, and 1st Ave North improvements via engineering agreements and infrastructure grant applications.

2 mentionsLast discussed Sep 28, 2026
MediumRoads

Pedestrian safety and sidewalk request on 30th Avenue South

A resident wants a sidewalk on the south side of 30th Ave S along Village Green Park, citing safety problems for pedestrians on Village Green Blvd. The request now sits with the council; no action was taken tonight.

1 mentionLast discussed Aug 24, 2026
MediumRoads

Citywide street striping and neighborhood overlays

The council approved change orders for the 2026 Citywide Striping Project and final wearing course overlays on streets in the Prairie Parkway 1st, Prairie Meadows 7th and Village Green 7th Additions. These are the final paving steps for those neighborhood streets.

1 mentionLast discussed Aug 10, 2026
HighRoads

Partridge Creek 2nd Addition street and utility improvements

The council took the first formal step toward Partridge Creek Addition street and utility improvements plus a stormwater pond and 28th Street South work, ordering plans and setting a public hearing.

5 mentionsLast discussed Jul 27, 2026
HighRoads

Center Avenue Reconstruction (8th to 10th St)

Temporary parking agreements and a change order moved forward for the Center Avenue rebuild — construction is progressing, with some temporary parking changes nearby.

2 mentionsLast discussed Jun 22, 2026
LowRoads

Right-of-Way Acquisition Authority

The council pre-authorized using court action to acquire right-of-way and property interests if negotiations fall through — keeping road and infrastructure projects on schedule.

1 mentionLast discussed Jun 22, 2026
HighRoads

Center Avenue Reconstruction (8th to 10th Street)

The council awarded the bid to rebuild Center Avenue between 8th and 10th Streets. Expect construction activity and traffic changes in that corridor once work gets underway.

1 mentionLast discussed Jun 8, 2026
MediumRoads

40th Avenue South Mill & Overlay and Roundabout

The council advanced multiple street projects, including the 40th Avenue South mill and overlay, with public hearings and bidding to follow. Expect construction and related assessments later this year.

7 mentionsLast discussed May 11, 2026