Railroad Crossing Safety and Quiet Zone Study

Summary

A feasibility study found none of Edina's five public crossings meet federal quiet zone minimums; building them would cost roughly $7 million and take 2-3 years after funding, with no federal grant program for quiet zones.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 16, 2026.

Impact analysis

💰Financial impact

About $7 million in unfunded crossing improvements would need a future CIP/budget decision.

✅Who benefits

Residents near the rail line disturbed by train horns, and drivers/pedestrians at safer crossings.